Skip to main content
News

Orangeburg County continuing broadband expansion

By February 28, 2022No Comments

Source: Johnson City Press

Orangeburg County Council Tuesday unanimously approved continuing to extend its broadband infrastructure throughout the county.

The council voted to spend $3,333,865 for the first phase of the broadband extension. The company doing the work will be Columbia-based Utility Service Contractors Inc.

The county also approved engaging with Missouri-based Graybar for $1,482,146 for the second phase of the broadband project.

The monies are a part of a $13.5 million U.S. Department of Agriculture ReConnect Program grant the county received that covers Cope, Felderville, portions of Santee, Neeses and North.

Phase 1 is eastern Orangeburg with a targeted completion by the end of the year, though there could be delays due to supply-chain issues.

Phase 2 is in western Orangeburg. Phase 2 should be completed by mid-year 2023.

Council also unanimously approved engaging St. Matthews-based Porth Construction for $3,496,190 to build the SC Gateway pump station and make sanitary sewer improvements

The project, which is expected to be complete by year’s end, will help connect the 1,322-acre South Carolina Gateway Industrial Park (formerly JAFZA Magna Park in Santee) to the county’s wastewater system.

In other matters, council gave unanimous first reading to provide a fee-in-lieu-of-tax incentive to a company publicly being identified under the name Project Stallion. Typically, projects are not publicly identified until deals are finalized.

Click here to continue reading…